Ordinance Number 2018-32
AN ORDINANCE DETERMINING THE LOWEST AND
BEST BIDS FOR THE NEW RESERVOIR IMPROVEMENT
PROJECT IN THE CITY OF ST. CLAIRSVILLE
AND AWARDING THE CONTRACTS TO
DN TANKS (CONTRACT A) AND TO
FERRI CONTRACTING CO., INC. (CONTRACT B)
WHEREAS, the City of St. Clairsville has received bids for the New Reservoir Improvement Project in the City of St. Clairsville; and
WHEREAS, City Council condones the action of the Director of Public Services in acting to advertise and accept the lowest and best bid for the New Reservoir Improvement Project in the City.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF ST. CLAIRSVILLE, OHIO:
Section 1: That the bid of DN Tanks, 11 Teal Road, Wakefield, Massachusetts, in the amount of $1,038,874.00 for Prestressed Concrete Water Utility Storage Tank in the City of St. Clairsville, and in accordance with the plans and specifications on file, is determined to be the lowest and best bid after competitive bidding for the Contract A portion of the project.
Section 2: That the bid of Ferri Contracting Co., Inc., 516 Hunt Club Drive, Canonsburg, Pennsylvania, in the amount of $585,468.00 for Site Improvements, Generator and Booster Station in the City of St. Clairsville, and in accordance with the plans and specifications on file, is determined to be the lowest and best bid after competitive bidding for the Contract B portion of the project.
Section 3: That the Mayor is authorized and directed to enter into contracts with DN Tanks and Ferri Contracting Co., Inc., for Prestressed Concrete Water Utility Storage Tank and Site Improvements, Generator and Booster Station, respectively, and the Director of Finance is authorized to expend the sums of $1,038.874.00 and $585,468.00, respectively, for this purpose.
Section 4: This Ordinance shall take effect and be in force from and after the earliest period allowed by the Charter of the City of St. Clairsville, Ohio.
City Council passed Ordinance Number 2018-32 on Monday, December 3, 2018.